Client Name: Lone Star College System

Sector: Higher Education

Project: LSCS Drop-off Plaza Enhancement

Duration: 10 Days

Contract Value: $300,098.78

Contract Delivery: Lone Star JOC Contract

Scope: Demolition of the existing pavers and sand base, demolition of existing landscape planting and the installation of a new concrete pavement, new landscape planting including irrigation, construction of  a new water fountain, new lighting and associated electric work.

Work Performed: E Contractors had to apply three layers of the acoustical treatment to match the existing, with each treatment taking a full day to cure and dry, before the next layer could be added.

 

Schedule and Delivery: The project was schedule for 1 week and took 10 days to complete due to  the drying time of the acoustical treatment used to match the existing.