Client Name: City of Webster

Sector: Government

Project: File Storage Room

Duration: 14 Days

Contract Value: $24,195.23

Contract Delivery: Choice Partners

Scope: Building the City of Webster a new secure file storage room for their city documents.

Work Performed: The City of Webster needed a secure place that was climate controlled to store their documents. An existing water tower location was picked by the City of Webster E Contractors built a 30′ x 24′ structure inside the existing water tower base which was raised off the floor. The structure was covered with 4 x 8 Hardier siding and had a mezzanine second floor that was accessed by an exterior staircase. The mezzanine was built to handle the load of other items that the City needed to store but did not need to be climate controlled. The exterior of the structure was painted and a security door installed. The interior of the structure was wired by the city electrician and then sheetrocked by E Contractors and painted.

Schedule and Delivery: The project was scheduled for a 2 week construction time frame and was completed on time.

Related projects
Leave Comment