Project: Dulles Elementary School Renovations

Client Name: Fort Bend ISD

Sector: K-12 Education

Contract Value: $1,399,200

Contract Delivery Method: Competitive Sealed Proposal

SCOPE OF WORK PERFORMED

E Contractors completed renovations on 28,000 sq. ft. of classrooms and hallways at Dulles Elementary School. The project included replacing existing millwork that served as corridor walls with a new corridor wall system that included new frames, doors and hardware; new acoustical ceilings; new millwork in each classroom; electrical services throughout the rebuilt areas; lights in the rooms and hallways; HVAC upgrades; installation of new data lines; upgrade of the fire alarm; new door signage; and new paint to the new as well as existing services.

SCHEDULE AND DELIVERY

This project was completed within a 90-day construction time as school had to be opened after summer break. E Contractors completed on time and on budget.