Client Name: Fort Bend ISD – Dulles ES Renovations

Sector: K-12 Education

Contract Value: $1,399,200

Contract Delivery Method: Competitive Sealed Proposal

SCOPE

Renovations of 28,000 sf of classrooms and hallways

WORK PERFORMED

E Contractors completed renovations on 28,000 sq. ft. of classrooms and hallways in the Dulles Elementary School. Tasks completed are as follows:

  1. Demolished the existing millwork that was installed for the corridor walls.
  2. Installed a new corridor wall system with new door frames/doors and hardware.
  3. Installed new acoustical ceilings in hallways.
  4. Installed new millwork in each classroom.
  5. Installed new electrical services and lights in the rooms and hallways.
  6. Installed new HVAC make up air unit with all new duct work going down the hallways.
  7. Installed new Data / Fire Alarm.
  8. Installed new door signage.
  9. Applied new paint to new and existing services.

SCHEDULE AND DELIVERY

This project was completed within the 90-day construction time, as planned.