Project: Clear Creek ISD – Seabrook Intermediate T-Buildings 

Client Name: Clear Creek ISD

Sector: K-12 Education

Project Delivered: Clear Creek ISD Seabrook Intermediate T-Buildings

Contract Value: $593,379.00

Contract Delivery Method: TCPN

Scope: Relocation of six classroom buildings and two restroom buildings located at the Clear Creek High School to Seabrook Intermediate.

Work Performed: In addition to moving of the eight buildings, E Contractors managed all the logistics including a new 800 amp electrical service to the site; installation of 700’ of new side walks including new canopies over the side walks; new alunimun decks, ADA ramps and walk ways; installation of new data, fire alarms lighting under the canopies and walkways; hooking up sewer and water to the (2) new restroom buildings; and installation of new skirting around all the buildings. At the site that they were removed, we demoed all the existing wood decks, canopies, plumbing and electrical wiring. Once everything was removed we striped the parking lot to new parking lay out that we provided.

Schedule and Delivery: Project schedule was 7 weeks to complete, and was completed within that time frame.

Leave Comment